JOB COMPLETION REPORT
As required by
FEDERAL AID IN FISHERIES RESTORATION ACT
TEXAS
Federal Aid Project No. F-6—R-12
FISHERIES INVESTIGATIONS AND SURVEYS OF THE WATERS 0F REGION S-B
Job No. C—l Pollution Studies
Project Leader: Charles T. Menu
J. Weldon Watson
Executive Director
Parks and Wildlife Department
Austin, Texas
Marion Toole Eugene At Walker
D—J Coordinator Assistant Director for Wildlife
January 21, 1965
JOB COMPLETION REPORT
State of Texas __fl
Project No: _E;é;§;lg__m‘ Name: £2§E§£§E§_EEE§§EES§£EOHS EESHH_
Survey§_of Ehgflflaters gfmfiegion
5-B
Job NO: C-l Title: Pollution Studies
_
m——m——— “aim—m
Period Covered: January 1, 1964 through December 31, l9§£
Objectives:
To determine the source and nature of natural or man-made pollutantS'which
affect the fish populations in public waters of Region 5~B:
Procedure:
During the progress of other jobs of the project, polluted waters were
watched for and investigated when found: Cases of water pollution reported
by sportsmen and game wardens were investigated:
Findings:
Lake Corpus Christi
On October 1, a fish kill due to the depletion of dissolved oxygen was
investigated in the upper reaches of Lake Corpus Christi, near Dinero Bridge:
In addition to a large number of smallmouth buffalo which lined a portion of
a slough, many channel and blue catfish, less than a pound in size, were found,
The kill was not considered to be detrimental to the overall fish pop-
ulation:
Recommendations:
This job should be continued so that future pollution cases may be investi—
gated and corrective action taken to abate it:
Prepared by Charles T: Menn Approved byge, s-fioeukanw u»/&L1P/.a
Project Leader Coordinator
Date January 21, 1965 __ Kenneth C: Jurgens